Mumbai:
NTPC Ltd. is setting up a coal-based thermal power
project of 750 MW (3x250 MW) at the site of Assam''s existing
non-operational Bongaigaon Thermal Power Station (TPS)
(4x60 MW), power minister Sushilkumar Shinde told the
Lok sabha.
NTPC
has concluded a transfer agreement with the Assam government
and the Assam Power Generation Corporation Ltd. (APGCL)
for transfer of the existing infrastructure of 240 MW
(4x60 MW) Bongaigaon Thermal Power Station of APGCL in
Assam to NTPC Ltd. and setting up of new 3x250 MW power
station at same location by NTPC Ltd.
Power
purchase agreement (PPA) has been signed by NTPC Ltd.
with Assam State Electricity Board (ASEB) on 30 May for
power supply from the project.
The
project is estimated to cost Rs4,496.24 crore (at 2006
prices). All key linkages/clearances for the project,
including environmental clearance have already been obtained.
The project is expected to be commissioned in 2010-11.
NTPC
can partner with a strategic partner who can bring the
expertise in manufacturing which in combination with NTPCs
strength in planning, Engineering, Project Management,
Operational Expertise can be used to develop a viable
equipment manufacturer and EPC contractor.
NTPC
has decided to take 44.6-per cent stake of Transformers
and Electricals Kerala, Ltd. (TELK) Kerala. An agreement
to this effect has been signed amongst NTPC, TELK and
the government of Kerala.
|